SR-303
Project Card
I-10 Papago - New traffic interchange TRAC # H713901
RTP Phase 2 Project Description Phase 1 of this project provides freeway-to-freeway access between Interstate 10 and Loop 303 north of I-10. The project also includes constructing two half diamond interchanges at Sarival Avenue and Citrus Road along with a frontage road to tie the two new interchanges into Cotton Lane, the former Loop 303 connection. As part of this project, crews are constructing the ramp frames for Phase II, which will connect I-10 to Loop 303 south of I-10.
Project Benefits West Valley drivers will have a freeway-to-freeway connection between Loop 303 and I-10 to accompany the Loop 303 improvements between I-10 in Goodyear to US 60 (Grand Avenue) in Surprise.
Schedule
2003
2004
2005
2006
2007
2008
2009
2010
2011
2012
2013
2014
2015
2016
Voter Approval
Open to traffic
Programmed Completion Date
Cost