I-10 Papago to Van Buren St - Addition of new northbound and southbound lanes TRAC # H726701
RTP Phase 1 Project Description The project improved 99th Avenue between Interstate 10 and Van Buren Street within the Cities of Avondale and Tolleson. The work included widening the existing street and improving major intersections. In addition, new traffic signals were installed, and curbs and storm drainage were improved.
Project Benefits Not only did the project enhance traffic flow on 99th Avenue, it also improved the connectivity between 99th Avenue and the I-10 frontage road system.
Schedule
2004
2005
2006
2007
2008
2009
2010
2011
2012
Voter Approval
Open to traffic
Programmed Completion Date
Cost