SR-85
Project Card
Milepost 130.7 to Milepost 137.0 - New 4-lane divided highway TRAC # H595507
RTP Phase 1 Project Description The project included constructing two new southbound roadway lanes and reconstructing the present roadway into two northbound lanes, to provide a four lane divided roadway. Other work included asphalt pavement milling and overlay, pipe and box culvert installation, guardrail and other related work.
Project Benefits The project helped to improve safety and reduce travel delays and was part of a longer-term access management solution for State Route 85.
Schedule
2003
2004
2005
2006
2007
2008
2009
2010
2011
Voter Approval
Open to traffic
Programmed Completion Date
Cost
Volumes